In May the foundations of the main building were laid on the plot in Tłuczań. Excavations, reinforcement and the first concrete footings marked out the outline of the future ashram.
On 12 May the concreting of the foundation footings began. A concrete pump and mixer trucks worked on the site, and the excavations were marked out with tape.
Two days later, on 14 May, the formwork and reinforcement of the foundation walls were already in place. In June the foundation walls were protected with insulation, and the outline of the building was clearly visible. The next stage is raising the walls.